4 new boilers in Fresenius Medical Care in Vršac
4 boilers, process equipment, pipeline and technical fluid for production in Fresenius Medical Care Vršac production complex has been completed.
1. steam boiler of 2,6 t/h
2. steam boiler of 2.6 t/h
3. hotwater boiler 1,8 MW
4. hotwater boiler 1.95 MW
Test was successfully performed and boiler room was put into operation.
News
01 Sep 2023
Due to the increased volume of work, we have expanded our professional team with two mechanical engineers, so that in addition to experienced [ ... ]
Details...25 Jan 2023
We are entering in 2023 with the same enthusiasm and desire to make 2023 as successful as the previous year was.
At the beginning of the [ ... ]
23 Dec 2022
We are starting the year 2022 with five signed contracts for the new boiler houses construction. Construction of the first "zero carbon [ ... ]
Details...20 Dec 2021
The year 2021 was extremely successful for Termičar, previously contracted jobs were completed. We are especially proud of our presence with [ ... ]
Details...04 Oct 2020
In the previous months, there was no break for Termičar doo, works from the beginning of the year which we started on Connecting water [ ... ]
Details...09 Nov 2019
Construction of a boiler room and installation of a boiler with a capacity 3200 kg / h of steam have been completed, as well as the accompanyin [ ... ]
Details...14 Oct 2019
Works on the construction of a steam boiler room and pipeline at the Cooper Tire & Rubber Company tire factory in Krusevac has begun.
Details...04 Oct 2019
Construction of hot water pipelines in the old boiler room and THR at the Hemofarm AD pharmaceutical factory in Vrsac has been completed
01 Apr 2019
The second phase of the installation of steam boiler with capacity 8 t / h of steam and boiler fittings in the factory Rauch Serbia doo in Koce [ ... ]
Details...25 Mar 2019
In the plant of AD Imlek dairy plant in Padinska Skela, the construction of pipelines and installations started up to the new dairy.
& [ ... ]