- Manufacturing hot water line in the village VELJKO VLAHOVIC, BECEJ, 400 m, year 2000
- Manufacturing hot water line in MALI RIT BECEJ, 600 m, 2000
- Manufacturing hot water line in REPUBLIKANSKA STREET, BECEJ, 1250 m, 2001
- Manufacturing steam line at PIK BECEJ, 700 m, year 2001
- Manufacturing substation hot water lines in CIM GAS Subotica, year 2002
- Manufacturing hot water line in a special hospital SVETI VRACEVI in Novi Kneževac , 400 m, year 2002
- Manufacturing hot water line in BLOCK 106 in Vrbas, 360 m, year 2002
- Manufacturing water supply in facility CERAMICS IGK POLET AD Novi Becej, year 2005
- Reparation of plumbing, steam lines and steam substation at PIK BECEJ Becej, year 2005
- Reconstruction of central heating facility HOTEL FANTAST Becej, year 2005
- Installing light balls in object CERAMICS, IGK POLET AD Novi becej, year 2005
- Manufacturing heating system in rubber factory AD GALAXY Ruma, year 2006
- Manufacturing cold water tank in the WEST PHARMACEUTICAL SERVICES in Belgrade and Kovin, year 2007
- Relocation calorifer heating in the production facility of fruit processing NECTAR doo Backa Palanka, year 2008
- Manufacturing an external steam distribution installation and condensate return in a dairy IMLEK AD Beograd, year 2009
- Manufacturing the installation for distribution sanitary water from a cogeneration facility in a dairy IMLEK AD Beograd, year 2009
- Manufacturing steam line and condensate return to the factory for processing soybean meal AD SOJAPROTEIN Becej, year 2009
- Manufacturing the cold water installation in dairy IMLEK AD Beograd, year 2009
- Manufacturing central heating system in dairy production plant IMLEK AD Beograd, year 2009
- Manufacturing central heating system in the main warehouse for the products storage of in Carlsberg Brewery Celarevo, year 2009
- Manufacturing radiator and central heating system in the raw materials storage in the Carlsberg Brewery Celarevo, year 2010
- Manufacturing new central heating system in factories manufacturing plant for processing soybean meal AD SOJAPROTEIN Becej, year 2011
- Manufacturing hot water lines and heaters for raw materials tanks in Krusevac SERBIA HENKEL, year 2011
- Adaptation of the central heating installation facility TSP, small packages and big-flight bags in the factory for processing soybean meal AD SOJAPROTEIN Becej, year 2012
- Manufacturing the new central heating system in Home Care HENKEL Krusevac SERBIA, year 2012
- Adaptation of artesian hot water substation for heating JODNA BANJA Becej, year 2012
- Manufacturing a new central heating system in the old and the new Factory for a meat processing factory NEOPLANTA AD Novi Sad, year 2013
- Manufacuring a new central heating system in AD SOJAPROTEIN Bečej, year 2013
- Manufacturing steam, water and comppressed air line in ALING CONEL DOO Gajdobra, year 2014
- Reconstruction of old pipelines in PREKON DOO Zrenjanin, year 2016
- Manufacturing steamline in leather factory LUXURY TANNERY Ruma, year 2016
- Manufacturing of main steamline Q=4000 kg/h for infusion products and propulsion of Energoblok 3 in HEMOFARM AD Vršac, year 2016
- Manufacturing thermal oil pipeline in TARKETT doo Bačka Palanka, year 2017
- Manufacturing cooling system in "Pardon", Investor PepsiCo Srbija Bački Maglić, year 2017
- Manufacturing ventilation and calorifer heating production facility in "Pardon", Investor PepsiCo Srbija Bački Maglić, year 2017
- Manufacturing of auxiliary heating of the wastewater purification pipeline in LUXURY TANNERY in Ruma, year 2017
- Manufacturing of heating of the processing plant in LUXURY TANNERY in Ruma, year 2017
- Installation of a supply tank in HENKEL SERBIA doo in Kruševac, year 2017
- Manufacturing calorifer heating, instalation of hot water steam and central heating system in HUTCHINSON Ruma, year 2017
- Reconstruction of substation EB3 in HEMOFARM AD Vršac, year 2018
- Reconstruction of the compressed air installation in NESTLE ADRIATIC S Surčin, year 2018
- Manufacturing of steam installations in IM GORANOVIĆ Nikšić, year 2018
- Installation of liquid carbon dioxide pipeline in ATLER FONTANA DOO Kikinda, year 2018
- Cold water pipeline with connection to the exchanger HEMOFARM AD Vrsac, year 2019
- Production of cold water pipeline and heating in WEST PHARMACEUTICAL SEVICES doo, Kovin year 2019
- Repair cooling pipeline of furnace in NEXE AD, Novi Bečej, year 2019
- Reconstruction of hot water pipelines of the old boiler room and construction of a new THR EB2-SK pipeline in Hemofarm AD Vrsac, year 2019
- Hot water pipeline from the boiler room to the high-bay warehouse, HEMOFARM AD Vršac, year 2020
- Installation of water vapor of 2 bar pressure NESTLE ADRIATIC S doo, Surčin, year 2020
- Connection of high water pressure hot air steam installation IMLEK AD, Padinska Skela, year 2020
- Instalation of the dryer NIGOS3 SOJAPROTERIN DOO, Bečej year 2020.
- Repair of steam and return condensate installation in facility I phase, NESTLE ADRIATIC S Surčin, year 2020
- Production of water vapor and compressed air system in facility Thomy NESTLE ADRIATIC S Surčin, year 2020
- Stainless steel chimney channel replacement in CARLSBERG DOO, Čelarevo, year 2021